Is typically not referred to as a buffer type in critical chain project management?

Respuesta :

dinosaurbarn
dinosaurbarn dinosaurbarn
  • 14-01-2018

The answer is Free Buffer. Project buffer, a not usual and the only one buffer to protect the project deadline;

Feeding buffer it is different types of buffers to protect parts of the critical chain. And resource buffer is a multiple artificial buffers that act as warning signals to assure that it is available of resources.

Answer Link

Otras preguntas

If a person is in front of a smooth surface from which a sound is reflected, the person would hear a sound that a. seems to come from behind the surface. b. has
Element used to make first atomic bomb
What is a postmodernist work more likely to have than a modernist work? a. a consistent rhyme scheme with repeating syllables b. a more playful attitude c. an e
What is 7 hundred x 10 in unit form?
Choose yes if you would document the item. Choose no if you would not document it. A graph that the writer constructed with information from another source. yes
As the percent of iron in an igneous rock increases its density will__________?
3kg 296 g + 5 kg + 326 g
How do you graph y= -x+5
Is a owl a specialists or generalists
Beneath earths surface, the temperature increases 10 degrees Celsius every kilometer. Suppose That the surface temperature is 22 degrees Celsius, and the temper