If 24 electricians can wire some new houses in 15 days, how many electricians would be required to do the job in 12 days?.

Respuesta :

shishirshrestha989
shishirshrestha989 shishirshrestha989
  • 04-01-2022

Answer:

here,

electrician/days

24 - 15

x(let). -12

direct proportion,

then,

exchange X up 24 down

or,24*15=12*X

or,24*15divided by 12=X

X=30

hence,30 electrician required to do complete in 12 days

Answer Link

Otras preguntas

What you a the contractile unit of the muscle fiber called?
Which title most clearly shows that the purpose of the text is to inform readers about the art displayed in a museum?
Helppp it’s due in a couple minutes!!!
some player heights are normally distributed with a mean 5.0 feet and a standard deviation of 0.3 feet. Let X. equals the height of a randomly selected student
How does the preamble promise succeeded?
1. Horace runs at a speed of 4.0 m/s for a distance of 300 meters. How much time did it take for Horace to run 300 meters?
sugar is produced in ___ of the chloroplast
Situation: Find the age of the skull to the nearest year. A hiker in Africa discovers a skull that contains 63% of its original amount of C 14. N = Noe 10 No =
Shania wants to purchase a book bag with an original price of $28.00. She also bought a necklace for $35.75. There is a storewide sale of 20% off and a tax of 7
Simplify to the power of 10. To the power of 8