if 12 people can finish a job by 5 days how many days will be required finish the same job by 10 people

Respuesta :

ishashunnny
ishashunnny ishashunnny
  • 01-09-2020

Answer:

4

Step-by-step explanation:

12p=5d

1p=5/12

10p=4.1666

≈4 days

Answer Link

Otras preguntas

Sally uses the pattern rule y = 4 + b to generate the first three outputs in the pattern. Which of the following is the fifth output in the pattern? Captionless
To improve the logic and flow of the essay, the writer should revise sentence 5 by replacing the word "money" with the word "dough. " deleting the sentence to c
Will give 5 stars on your answer and a thank you.
how does cardon enter the soil
Question 2 help meeee pleaseee Thank you
Walmart sells birthday cakes for. $18. After 3 days,they markdown the cakes by 45% . What is the discounted price after 3 days has passed?
how should the US reduce the economic inequality?
Write the expression in exponential form.
A balloon rises to 100 feet in 4 minutes and 125 feet in 5 minutes. Write and solve an equation to find the distance the balloon rises in 8 minutes. Use d for d
Which example of Louisiana exports generates the greatest annual revenues, totaling $75 billion? O oil and natural gas O cotton and sugarcane O cattle and chick